Sorting of the waste:
The works foreman allocated to the construction site is responsible for the good organization and for the good progress of the evacuation of the waste following their natures:
- The products of sluggish clearings (earth, rock, stones etc.) will be stored seen by re-use on the construction site there following the agreement of the project manager and according to the utility or not. Otherwise, they will be evacuated in municipal garbage dump or given to the Municipality(Commune) to bank up roads depending of materials. Lastly materials will be evacuated in our discharge(dump) of TERRASSON.
- The remains of coated sluggish (bottom of truck, spare capacity of construction site) return in our deposit(warehouse) of TERRASSON or they will be stored with of the other one while waiting for to be crushed for re-use.
- The remains of emulsion: return in tanks in our deposit(warehouse) to TERRASSON.
- The sluggish planings will be stored in a deposit(warehouse) with the agreement of the project owner for re-use on the construction site in elevations or in layer of shape. The remain will be evacuated in our deposit(warehouse) of TERRASSON for re-use.
- The waste sluggish concrete (borders, concrete, buzzard of purification, concrete of power plant etc.) will have returned in our deposit(warehouse) to TERRASSON to be crushed there seen by re-use.
Miscellaneous :
- Bombs(Sprays) of construction site: return to TERRASSON in trucks of waste treated(handled) by the company ONIX.
- End of pipe PVC: return to TERRASSON in trucks of waste treated(handled) by the company ONIX.
- Jars of resin: return to TERRASSON in trucks of waste treated(handled) by the company ONIX.
- All the small bulky waste of construction site (picket wood, picket iron, plastic bag, bag cement etc.) Return to TERRASSON in trucks of waste treated(handled) by the company ONIX.
|